Components
of Integrated Solid Waste Management
Initiated under Clean Kerala Project
|
1. Segregated collection
(No. of wards covered) |
started in 27 wards |
| 2. Number of vehicles used for Transportation |
Kudumbashree Autos - 14
Triller - 6
Dumper placer - 1
Hand carts - 25
|
| 3. Number of Sanitary workers engaged |
191 contingent workers, 50 CLR, 37 holding
CLR are engaged for the same ( 1 supervisor & 18 CDS
workers are engaged in the plant) |
| 4. Number of Processing plants |
1 |
- Processing Techniques installed and quantity of waste
processed
|
Windrow Composting plant : 10 Tonne
|
- Run by Municipality / Entrepreneur
|
Municipality _ Palakkad Nagarasabha Sucheekarana
Samithi(PNSS) - Under the supervision of IRTC |
|
Green belt formation is completed with the
help of social forestry dept. |
|
constructed |
|
drainage construction partially completed |